Replies: 7 comments
-
Welcome :)
Have a look at It's a demo module only because in my experience, the exact definition of what a budget commitment is is highly variable from one company to another.
That is another possible approach indeed: instead of having a SQL view on unvoiced PO/PR, one can imagine a kind of budget/commitment accounting. I'm not aware of any module that does that. |
Beta Was this translation helpful? Give feedback.
-
Thank you @sbidoul for pointing to where I left forgotten. Ya, I think I should have read it from your slide :) I think you understand my point very well, as you mentioned That's what we did previously (v8), because of the requirement which want the SAP like feature, tracebility, costcenter, budget plan, budget check, we end up with a lot of development (which I don't like). We did make PR/PO/EX and SO to create commit line (account.analytic.line, type=pr_commit, po_commit, etc..), commitment transition in granular level (i.e., partially). Meaning next document create new commit line, the prev document will also create counter negative commit line. And reason Please allow me to discuss out loud. I do like what mis_builder has done. But it is not using the same method in getting the commitment vs actuals, and so it won't be single fact. And as report is not something persistent, we can not use it to actively check/block budget, right? I am looking into create this kind of budget transition solution, at the same time, want to make it elegant like mis_builder or even being extension out of it. Is it something you would ever need? Anything I missed that you want to remarks? |
Beta Was this translation helpful? Give feedback.
-
@kittiu regarding the check/blocking of PO against available budget, we usually do it with MIS Builder, by flagging a column in a mis report instance as the one that needs to be checked, and then using method Regarding a budget accounting system, you can do it as an extension of mis_builder_budget, or as a separate system. As long as you can provide views that work as alternative sources for mis builder (like mis_builder_demo or account_move_budget do) it will work with mis buidler for display and calculation. |
Beta Was this translation helpful? Give feedback.
-
@kittiu check also #154. My idea is to use that as base for creating extension modules for each of the possible future incoming/expenses, creating entries in that table. For example, contract module generates entries for next year, and when the invoice is generated, that entry is removed or reversed (to see what is more interesting). The same can be done for sales, or for purchase (with reverse sign). Maybe this can be serve also for your purpose. |
Beta Was this translation helpful? Give feedback.
-
Great! That make all sense to me. Thanks you very much! |
Beta Was this translation helpful? Give feedback.
-
@sbidoul
Like governmental budgeting, given an organization with organization chart (i.e., BU > Dept > Costcenter), my goal is to being flexible to set budget by Dept, use budget by Costcenter and lock budget by BU. Then the report is able to show commitment, actual, balance, sum up in any level of org chart + account code. Actually, about org's chart fields is another topic that I can't find solution by using Odoo's analytic. But I will just focus on analytic for now. Sorry if the question sound diverged from the intention of mis_builder. But I would think it I could make it fit into the great mis_builder, it will be awesome! |
Beta Was this translation helpful? Give feedback.
-
Hi @kittiu,
Yes, using analytic account field on move lines and budget lines (and additional fields for other analytic dimensions). The filtering is done here.
It is not available out of the box, you need to implement it. |
Beta Was this translation helpful? Give feedback.
-
Hello @sbidoul @jbeficent
cc @wipawii
First of all, I am new to these modules. But I did looking into both account_move_budget and mis_builder_budget. If I am not wrong, the objective of both are into reporting purposes by comparing the Actual (from move lines) VS Budget Amount. These are all working well by the modules.
I am wondering if you have been looking into use case where we need to track the PR/PO budget as commitment too?
For example, i.e., a project budgeted at 1,000 USD
And also, once the Budget Balance is less, to also mechanism to Block or Warn user when PR/PO/Invoice makes Budget Balance < 0.0
Then, we can create some kind of budget monitoring report, that show all, pr commit, po commit, inv actual, consumed (pr+po+inv) and balance (budget-consumed)
Thank you!
PS: I though I have seen it somewhere about transfer budget commitment between document, but couldn't find it...
Beta Was this translation helpful? Give feedback.