Notifications
You must be signed in to change notification settings - Fork 8
Meeting Notes #11
elif-caliskan edited this page May 7, 2019
·
4 revisions
- Location: Boğaziçi University, Computer Engineering Department, Lounge
- Date: 07.05.19
- Time: 17.00-17.45
- Bahadır Hocamoğlu (Communicator)
- Baturalp Yörük
- Elif Çalışkan
- Ege Başural
- Emre Demircioğlu
- Gürkan Demir
- İbrahin Özgürcan Öztaş
- İsmail Levent Baş
- Muhammed Bera Kaya
- Taha Eyup Korkmaz
- 2.1 Read the Milestone2 assignment.
- 2.2 Go over some Milestone documents of previous years to gain insight about the report.
- 2.3 Talk about the status of project and decide on the path to follow.
- 3.1 Went over previous years' Milestone reports:
-
3.2 Assigned team members for each part of Milestone2.
- Executive Summary
- List and status of deliverables
- Evaluation of the status of deliverables
- Summary of work done by each team member
- Project plan
- Evaluation of tools
- API URL
- 3.3 Decided to use LaTeX and for that, we can make use of our previous Milestone report template in Overleaf.
Act.No | Person | Action | Deadline |
---|---|---|---|
1 | Baturalp Yörük, Bahadır Hocamoğlu, Elif Çalışkan, Emre Demircioğlu |
Executive Summary for Milestone2 | 12.05.19 Sunday @20.59 |
2 | Taha Eyüp Korkmaz, Ege Başural, Muhammed Bera Kaya, İbrahim Özgürcan Öztaş |
Deliverables for Milestone2(list and status + evaluation) | 12.05.19 Sunday @20.59 |
3 | Everyone | Summary of work done for Milestone2 | 12.05.19 Sunday @20.59 |
4 | İsmail Levent Baş, Gürkan Demir |
Project Plan, Tool Evaluation, API URL | 12.05.19 Sunday @20.59 |
- Bahadır Hocamoğlu (Communicator)
- Baturalp Yörük
- Cemal Aytekin
- Ege Başural
- Elif Çalışkan
- Emre Demircioğlu
- Gürkan Demir
- İsmail Levent Baş
- Muhammed Bera Kaya
- Taha Eyup Korkmaz
İbrahim Özgürcan Öztaş
- Project Description
- Project Plans
- Questions and Answers about Project
- Requirements Analysis
- User Personas & Stories
- User Scenarios & Mockups
- Diagrams
- CmpE352
- CmpE451